Calculator Library / Lean Construction
Track the reliability of weekly work plans, see the trend in percent plan complete, and rank the reasons for missed assignments so the team knows what to fix next.
Tool
PPC = assignments completed as promised / assignments planned
| Week | Planned | Completed | PPC | Missed | Materials | Prerequisite work | Design info / RFI | Labor / crew | Equipment | Weather | Owner / inspector | Other | Unassigned |
|---|
Enter the count of missed assignments for each reason. "Unassigned" shows missed assignments that do not yet have a reason. Data saves in this browser only and nothing is sent to a server.
Summary
Trend
Pareto
Instructions
The tracker records the weekly work plan's reliability and the reasons assignments were missed. It calculates PPC by week, compares the first half of the record with the second, and ranks the reasons in a Pareto chart, so a planning team can see whether its promises are getting more reliable and what to fix next.
Use it in the weekly work plan meeting and to report the reliability of planning to the project team.
| Measure | Formula | Meaning |
|---|---|---|
| Weekly PPC | Completed / Planned | Share of committed assignments completed as promised. |
| Missed | Planned − Completed | Assignments not completed as promised in the week. |
| Unassigned | Missed − sum of reason counts | Missed assignments that still need a reason. |
| Overall PPC | Total completed / total planned | Reliability over the whole period, weighted by assignments. |
The pre-loaded data show planned assignments of 40, 42, 38, 41, 44, 40, 43, and 42, with 26, 28, 26, 31, 34, 33, 36, and 35 completed. PPC rises from 65% to about 83%. In the first three weeks materials (14) and prerequisite work (10) are the top reasons, which points the team toward a constraint review in the lookahead.
Average PPC in the first half of the record is about 69% and in the second half about 82%. The improvement came from committing only to work that was ready, and not from asking crews to work harder.
Percent plan complete (PPC) is the number of weekly assignments completed as promised divided by the number planned, expressed as a percentage. It is a Last Planner System measure of how reliable a team's commitments are, and it is used with reasons for variance to find what disrupts the work.
Targets vary by project and maturity, and the most useful comparison is with your own trend. Many teams treat a PPC in the range of 80 percent as a reasonable reference for a mature process, and use the reference line in the tool as a starting point, adjusting it to your own goals.
They are the recorded causes of missed assignments, such as materials not on site, prerequisite work incomplete, design information or requests for information outstanding, labor shortage, equipment, weather, or owner and inspector delays. Counting them by category shows the most common causes, which the team then works to remove.
No. The tracker saves in your own browser using local storage and does not send anything to a server. Use Clear all to remove it, and keep entries to counts rather than names of individuals.