Tool

Record each week's plan, completions, and reasons for misses

PPC = assignments completed as promised / assignments planned

WeekPlannedCompletedPPCMissed MaterialsPrerequisite workDesign info / RFILabor / crewEquipmentWeatherOwner / inspectorOtherUnassigned

Enter the count of missed assignments for each reason. "Unassigned" shows missed assignments that do not yet have a reason. Data saves in this browser only and nothing is sent to a server.

Summary

Reliability of promises

Weeks tracked
0
Overall PPC
--
Latest week
--
First half
--
Second half
--
Top reason
--

Trend

Weekly PPC

Pareto

Why assignments were missed

Instructions

How to use this app

  1. At the end of each week, count the assignments the crews committed to and how many were completed as promised.
  2. For each missed assignment, choose the main reason from the list and enter the counts by reason.
  3. Review the Pareto chart at the weekly planning meeting and pick the top reason to work on.
  4. Watch the trend, and check that overall progress and completed work are also improving, since PPC can be raised by promising less.
  5. Use it to learn as a team, not to rank crews.

What This Percent Plan Complete Tracker Helps You Decide

The tracker records the weekly work plan's reliability and the reasons assignments were missed. It calculates PPC by week, compares the first half of the record with the second, and ranks the reasons in a Pareto chart, so a planning team can see whether its promises are getting more reliable and what to fix next.

Use it in the weekly work plan meeting and to report the reliability of planning to the project team.

How It Works

MeasureFormulaMeaning
Weekly PPCCompleted / PlannedShare of committed assignments completed as promised.
MissedPlanned − CompletedAssignments not completed as promised in the week.
UnassignedMissed − sum of reason countsMissed assignments that still need a reason.
Overall PPCTotal completed / total plannedReliability over the whole period, weighted by assignments.

Worked Example: Eight Weeks

The pre-loaded data show planned assignments of 40, 42, 38, 41, 44, 40, 43, and 42, with 26, 28, 26, 31, 34, 33, 36, and 35 completed. PPC rises from 65% to about 83%. In the first three weeks materials (14) and prerequisite work (10) are the top reasons, which points the team toward a constraint review in the lookahead.

Average PPC in the first half of the record is about 69% and in the second half about 82%. The improvement came from committing only to work that was ready, and not from asking crews to work harder.

Limits and Good Practice

Percent Plan Complete Tracker Frequently Asked Questions

What is percent plan complete?

Percent plan complete (PPC) is the number of weekly assignments completed as promised divided by the number planned, expressed as a percentage. It is a Last Planner System measure of how reliable a team's commitments are, and it is used with reasons for variance to find what disrupts the work.

What is a good PPC?

Targets vary by project and maturity, and the most useful comparison is with your own trend. Many teams treat a PPC in the range of 80 percent as a reasonable reference for a mature process, and use the reference line in the tool as a starting point, adjusting it to your own goals.

What are reasons for variance?

They are the recorded causes of missed assignments, such as materials not on site, prerequisite work incomplete, design information or requests for information outstanding, labor shortage, equipment, weather, or owner and inspector delays. Counting them by category shows the most common causes, which the team then works to remove.

Is my data stored anywhere?

No. The tracker saves in your own browser using local storage and does not send anything to a server. Use Clear all to remove it, and keep entries to counts rather than names of individuals.